Wireless Network Expansion Tech Briefing—November 2013

Note: This article was originally published on our website in November 2013 and is being added to this blog for historical purposes.

Campus Housing

We are installing cabling and network switches in Campus Village for Wireless Access Points.

  • CVA is 95% complete
  • CVB testing cabling work and mounting access points
  • CVC starting cabling work

Main Campus

In October the following buildings were upgraded to Cisco Wireless:

  • UPD/HR
  • SSC
  • Admin
  • AS House

The following buildings are scheduled to be upgraded in November:

  • IRC—Complete
  • DHM—Complete
  • Student Union East
  • WSQ
  • SCI
  • BBT

King Library

Ongoing tuning of existing WAPs to optimize performance. We added 25 WAPs to the library in October.